608891 |
GARDNER- RESURFACING AND RUMBLE STRIP INSTALLATION ON ROUTE 140 |
Resurfacing |
CONSTRUCTION |
|
609279 |
GARDNER- ROUNDABOUT CONSTRUCTION AT ELM STREET, PEARL STREET, CENTRAL STREET AND GREEN STREET |
Hwy Reconstr - No Added Capacity |
CONSTRUCTION |
|
610729 |
GARDNER- WESTMINSTER- PAVEMENT PRESERVATION AND RELATED WORK ON ROUTE 2 |
Resurfacing DOT Owned Non-Interstate |
CONSTRUCTION |
|
600774 |
GARDNER- TEMPLETON- BRIDGE REPLACEMENT, BR# G-01-002=T-02-006 BRIDGE STREET/TURNER ROAD OVER THE OTTER RIVER |
Bridge Replacement |
DESIGN |
|
609108 |
GARDNER- BIKE PATH BRIDGE CONSTRUCTION, NORTH CENTRAL PATHWAY OVER ROUTE 140 |
Bikeway/Bike Path Construction |
DESIGN |
2027 |
610672 |
GARDNER- ELM STREET RESURFACING AND SIDEWALK IMPROVEMENTS (SRTS) |
Roadway - Reconstr - Sidewalks and Curbing |
DESIGN |
2025 |
613260 |
GARDNER- SHARED-USE PATH CONSTRUCTION, NORTH CENTRAL PATHWAY EXTENSION |
Bikeway/Bike Path Construction |
DESIGN |
|
613298 |
GARDNER- BRIDGE REHABILITATION, G-01-021 (1FL), MILL STREET OVER BAKER BROOK |
Bridge Reconstruction/Rehab |
DESIGN |
2029 |
613801 |
TEMPLETON TO LANCASTER- GUIDE AND TRAFFIC SIGN REPLACEMENT ON A SECTION OF ROUTE 2 |
Structural Signing |
DESIGN |
|
602097 |
GARDNER- RESURFACING AND RELATED WORK ON A SECTION OF ROUTE 101 (PEARL STREET) |
Resurfacing |
COMPLETE |
|
602166 |
GARDNER- WESTMINSTER- ROUTE 140 COLD PLANE OVERLAY, BOX WIDENING, SIGNAL RECONSTRUCTION, CHANNELIZATION GREEN ST. TO SCENIC DR. |
Hwy Reconstr - Minor Widening |
COMPLETE |
|
602622 |
GARDNER- RESURFACING, GREEN STREET FROM MATTHEWS STREET NORTHERLY TO ROUTE 140 |
Resurfacing |
COMPLETE |
|
602837 |
DISTRICT 2- DISTRICT 3- GUARDRAIL REFURBISHMENT AND DELINEATION PROJECT ON ROUTE 2 FROM LITTLETON TO PHILLIPSTON |
Guard Rail & Fencing |
COMPLETE |
|
602946 |
GARDNER- WINCHENDON- CONSTRUCTION OF A BICYCLE PATH, NORTH CENTRAL PATHWAY (PHASE III) |
Bikeway/Bike Path Construction |
COMPLETE |
|
603747 |
GARDNER- BRIDGE REPLACEMENT, G-01-017, WINTER STREET & G-01-022, MILL STREET OVER BAKER BROOK |
Bridge Replacement |
COMPLETE |
|
603975 |
GARDNER- BRIDGE REPLACEMENT, G-01-023, TRAVERS STREET OVER TRAVERS POND OUTLET |
Bridge Replacement |
COMPLETE |
|
604061 |
GARDNER- WINCHENDON- PEDESTRIAN & BIKE TRAIL CONSTRUCTION & RELATED WORK (NORTH CENTRAL PATHWAY - PHASE IV) INCLUDES W-39-016 & RESURFACING (GARDNER - PHASE III) |
Bikeway/Bike Path Construction |
COMPLETE |
|
604162 |
GARDNER- BRIDGE SUPERSTRUCTURE REPLACEMENTS, G-01-035 & G-01-036, ROUTE 2 OVER ROUTE 68 |
Structures Maintenance |
COMPLETE |
|
604201 |
GARDNER- WESTMINSTER- RESURFACING AND RELATED WORK, ROUTE 2 TO ROUTE 140N |
Resurfacing |
COMPLETE |
|
604966 |
FITCHBURG- GARDNER- LANCASTER- LEOMINSTER- WESTMINSTER- TRAFFIC SIGN REPLACEMENT & UPGRADE ON STATE ROUTE 2 |
Sign Installation/Upgrading |
COMPLETE |
|
605579 |
GARDNER- RESURFACING & RELATED WORK ON ROUTE 140 |
Resurfacing |
COMPLETE |
|
607252 |
GARDNER- RESURFACING & RELATED WORK ON MATTHEW STREET |
Hwy Reconstr - Restr and Rehab |
COMPLETE |
|
608060 |
GARDNER- SHREWSBURY- STORMWATER IMPROVEMENTS ALONG ROUTE 68 AND ROUTE 70 |
Sewer and Water |
COMPLETE |
|
608188 |
GARDNER- LEOMINSTER- STERLING- INTERSECTION IMPROVEMENTS AT 3 LOCATIONS |
Traffic Signals |
COMPLETE |
|
608864 |
GARDNER- BRIDGE REPLACEMENT, G-01-008, PLEASANT STREET OVER THE B&M RAILROAD |
Bridge Reconstruction/Rehab |
COMPLETE |
|
608888 |
GARDNER- RESURFACING AND RELATED WORK ON PEARSON BOULEVARD |
Resurfacing |
COMPLETE |
|