| 603722 |
LEXINGTON- BRIDGE REPLACEMENT, L-10-010, ROUTE 2A (MARRETT ROAD) OVER I-95/ROUTE 128 |
Bridge Replacement |
CONSTRUCTION |
|
| 610719 |
BURLINGTON TO TYNGSBOROUGH- PAVEMENT PRESERVATION ON ROUTE 3 |
Limited Access Pavement Preservation |
CONSTRUCTION |
|
| 611937 |
LEXINGTON- CONSTRUCTION OF A PRE-ENGINEERED EQUIPMENT REPAIR GARAGE AT THE LEXINGTON DEPOT |
Vertical Construction (Ch 149) |
CONSTRUCTION |
|
| 613466 |
ARLINGTON- LEXINGTON- SCHEDULED SUBSTRUCTURE REPAIRS L-10-017, L-10-020, A-10-020, A-10-012 |
Bridge Maintenance |
CONSTRUCTION |
|
| 43550 |
LEXINGTON- ROADWAY RECONSTRUCTION ON A SECTION OF MARRETT ROAD (ROUTE 2A) |
Roadway Modernization |
DESIGN |
|
| 601936 |
LEXINGTON- MILTON- REVERE- INSTALLATION OF 8 - 10,000 GALLON ABOVE GROUND CaCl2 STORAGE TANKS AT 4 LOCATIONS |
Miscellaneous/No Prequal |
DESIGN |
|
| 602083 |
DISTRICT 4- RAMP RESURFACING AND RELATED WORK ON A SECTION OF ROUTE I-95 (128) FROM LYNNFIELD TO WELLESLEY |
Resurfacing |
DESIGN |
|
| 602308 |
LEXINGTON- LINCOLN- REPLACEMENT OF CONCRETE MEDIAN BARRIER ON A SECTION OF ROUTE 2 (CAMBRIDGE TURNPIKE) |
Safety Improvements |
DESIGN |
|
| 602353 |
LEXINGTON- RECONSTRUCTION OF EMERY PARK IN DEPOT SQUARE |
Miscellaneous/No Prequal |
DESIGN |
|
| 602915 |
DISTRICT 4- RESURFACING AND RELATED WORK IN AREA "B" |
Resurfacing |
DESIGN |
|
| 608495 |
CONCORD- LEXINGTON- LINCOLN- RESURFACING AND RELATED WORK ON ROUTE 2A |
Pavement Rehabilitation |
DESIGN |
2030 |
| 613178 |
LEXINGTON- DECK REPLACEMENT, L-10-019 (2DW, 2DX), STATE ROUTE 2/CONCORD TURNPIKE OVER PLEASANT STREET |
Bridge Deck Replacement |
DESIGN |
|
| 613695 |
LEXINGTON- ROADWAY RECONSTRUCTION ON HARTWELL AVENUE AND BEDFORD STREET |
Roadway Modernization |
DESIGN |
|
| 600703 |
LEXINGTON- BRIDGE REPLACEMENT, L-10-009, ROUTE 2 (EB & WB) OVER ROUTE I-95/ROUTE 128 (DESIGN-BUILD) |
Bridge Replacement |
COMPLETE |
|
| 602041 |
BURLINGTON- LEXINGTON- RESURFACING AND RELATED WORK ON A SECTION OF ROUTE I-95 (ROUTE 128) |
Resurfacing |
COMPLETE |
|
| 602133 |
LEXINGTON- SIGNAL UPGRADE AT ROUTE 2A AND WALTHAM STREET |
Traffic Signal Upgrades |
COMPLETE |
|
| 604628 |
LEXINGTON- RESURFACING & RELATED WORK ON ROUTE 2 |
Resurfacing |
COMPLETE |
|
| 604755 |
LEXINGTON- BRIDGE PRESERVATION, L-10-017, SPRING STREET OVER ROUTE 2 |
Structures Maintenance |
COMPLETE |
|
| 604896 |
ARLINGTON- BELMONT- CAMBRIDGE- LEXINGTON- LINCOLN- SIGN REPLACEMENT & IMPROVEMENTS ON STATE ROUTE 2 |
Sign Installation/Upgrading |
COMPLETE |
|
| 604937 |
LEXINGTON- NEWTON- WALTHAM- WELLESLEY- WESTON- TRAFFIC SIGN REPLACEMENT ON I-95, FROM WELLESLEY (ROUTE 9) TO LEXINGTON (ROUTES 4/225) APPROX. 13 MILES |
Structural Signing |
COMPLETE |
|
| 605018 |
BURLINGTON- LEXINGTON- READING- WOBURN- TRAFFIC SIGN & GUIDE REPLACEMENT ON I-95 (SR 128) |
Sign Installation/Upgrading |
COMPLETE |
|
| 605870 |
LEXINGTON- SAFE ROUTES TO SCHOOL (BOWMAN SCHOOL) |
Roadway Modernization |
COMPLETE |
|
| 606031 |
LEXINGTON- CABLE BARRIER INSTALLATION ALONG ROUTE 2 |
Guard Rail & Fencing |
COMPLETE |
|
| 606170 |
LEXINGTON- BURLINGTON- INTERSTATE MAINTENANCE & RELATED WORK ON I-95 |
Resurfacing |
COMPLETE |
|
| 606432 |
LEXINGTON- BURLINGTON- WOBURN- STONEHAM- READING- WAKEFIELD- LYNNFIELD- EXPANSION OF FIBER & CCTV ON I-95 |
Intelligent Transportation Sys |
COMPLETE |
|
| 607409 |
LEXINGTON- RECONSTRUCTION ON MASSACHUSETTS AVENUE, FROM MARRETT ROAD TO PLEASANT STREET |
Hwy Reconstr - Restr and Rehab |
COMPLETE |
|
| 608379 |
LEXINGTON- BELMONT- ARLINGTON- CAMBRIDGE- PAVEMENT PRESERVATION ON ROUTE 2 |
Resurfacing DOT Owned Non-Interstate |
COMPLETE |
|