607688 |
MONSON- PALMER- BRIDGE REPLACEMENT, M-27-022=P-01-033, PARK ST/BOSTON ROAD EAST (US 20) OVER THE QUABOAG RIVER |
Bridge Replacement |
CONSTRUCTION |
|
608846 |
MONSON- BRIDGE REPLACEMENT, M-27-015, OLD WALES ROAD OVER CONANT BROOK |
Bridge Replacement |
CONSTRUCTION |
|
30512 |
MONSON- BRIDGE REPLACEMENT, BR# M-27-012 HOVEY ROAD OVER CONRAIL |
Bridge Replacement |
DESIGN |
|
601171 |
MONSON- ROADWAY RECONSTRUCTION ON A SECTION OF THOMPSON STREET |
Hwy Reconstr - Restr and Rehab |
DESIGN |
|
601728 |
MONSON- ROADWAY RECONSTRUCTION ON WALES ROAD FROM MOULTON HILL ROAD TO THE WALES T.L. |
Hwy Reconstr - Major Widening |
DESIGN |
|
604136 |
MONSON- PALMER- BRIDGE REPLACEMENT, M-27-007=P-01-007, STATE AVENUE OVER THE QUABOAG RIVER |
Bridge Replacement |
DESIGN |
2026 |
612160 |
MONSON- PALMER- BRIDGE REPLACEMENT, M-27-008=P-01-008, ROUTE 32 OVER QUABOAG RIVER |
Bridge Replacement |
DESIGN |
2026 |
612984 |
MONSON- RESURFACING AND RELATED WORK ON MAIN STREET (ROUTE 32) |
Roadway - Reconstr - Sidewalks and Curbing |
DESIGN |
2029 |
613139 |
MONSON- SUPERSTUCTURE REPLACEMENT OF BRIDGE M-27-026, STAFFORD HOLLOW ROAD OVER NECRR |
Bridge Reconstruction/Rehab |
DESIGN |
2028 |
613296 |
MONSON- BRIDGE REPLACEMENT, M-27-030 (68H), BUNYAN ROAD OVER CHICOPEE BROOK |
Bridge Replacement |
DESIGN |
|
600968 |
DISTRICT 2- DRAINAGE BETTERMENTS AT VARIOUS LOCATIONS |
Miscellaneous/No Prequal |
COMPLETE |
|
601502 |
MONSON- RECONSTRUCTION OF LOWER HAMPDEN ROAD, FROM HAMPDEN T.L. TO ELM STREET (4.13 MILES) INCLUDES M-27-034 |
Hwy Reconstr - Minor Widening |
COMPLETE |
|
602076 |
MONSON- RECONSTRUCTION OF HOSPITAL ROAD FROM MACOMBER ROAD TO PALMER ROAD (ROUTE 32) , 1.2 KILOMETERS |
Hwy Reconstr - No Added Capacity |
COMPLETE |
|
603960 |
MONSON- BRIDGE REHABILITATION, M-27-010, HOSPITAL ROAD OVER CHICOPEE BROOK |
Bridge Reconstruction/Rehab |
COMPLETE |
|
606663 |
MONSON- PALMER- RESURFACING & RELATED WORK ON ROUTE 32, FROM MM 5.69 TO MM 6.88 AND FROM MM 8.24 TO MM 8.80 AT ROUTE 20 (1.69 MILES) |
Resurfacing |
COMPLETE |
|