Projects
Filter projects by: Project Phase TIP Status
All Projects All Projects
Construction Current Fiscal Year
Design Future Years
Complete Not Programmed
Number Description Project Type Status TIP Year
604996 WOBURN- BRIDGE REPLACEMENT, W-43-017, NEW BOSTON STREET OVER MBTA New Bridge CONSTRUCTION
610726 MEDFORD- READING- SOMERVILLE- STONEHAM- WINCHESTER- WOBURN- INTERSTATE PAVEMENT PRESERVATION ON I-93 Resurfacing Interstate CONSTRUCTION
612034 WOBURN- INTERSTATE PAVEMENT PRESERVATION AND RELATED WORK ON I-95 Resurfacing Interstate CONSTRUCTION
600707 WOBURN- BRIDGE REPAIRS AND RELATED WORK, BR# W-43-036, ROUTE I-93 OVER MONTVALE AVENUE Bridge Reconstruction/Rehab DESIGN
602083 DISTRICT 4- RAMP RESURFACING AND RELATED WORK ON A SECTION OF ROUTE I-95 (128) FROM LYNNFIELD TO WELLESLEY Resurfacing DESIGN
604215 MEDFORD- READING- SOMERVILLE- STONEHAM- WOBURN- TRAFFIC MANAGEMENT SERVICES FOR THE DEMOCRATIC CONVENTION RESPONSE, I-93 SB Miscellaneous/No Prequal DESIGN
604216 MEDFORD- SOMERVILLE- STONEHAM- WOBURN- TEMPORARY EXTENSION OF HIGH OCCUPANCY VEHICLE LANE FOR THE DEMOCRATIC NATIONAL CONVENTION, I-93 SB Miscellaneous/No Prequal DESIGN
605013 WOBURN- NOISE BARRIER CONSTRUCTION ON I-93 Hwy Reconstr - Restr and Rehab DESIGN
605605 WOBURN- READING- STONEHAM-WAKEFIELD- INTERCHANGE IMPROVEMENTS TO I-93/I-95 Hwy Reconstr - Added Capacity DESIGN
608067 WOBURN- BURLINGTON- INTERSECTION RECONSTRUCTION AT ROUTE 3 (CAMBRIDGE ROAD) & BEDFORD ROAD AND SOUTH BEDFORD STREET Hwy Reconstr - Minor Widening DESIGN 2025
610662 WOBURN- ROADWAY AND INTERSECTION IMPROVEMENTS AT WOBURN COMMON, ROUTE 38 (MAIN STREET), WINN STREET, PLEASANT STREET AND MONTVALE AVENUE Hwy Reconstr - No Added Capacity DESIGN 2029
613275 BEVERLY- BURLINGTON- DANVERS- GLOUCESTER- WOBURN- BRIDGE PRESERVATION AT 9 BRIDGES CARRYING STATE ROUTE 128 Bridge Preservation DESIGN 2027
613318 BURLINGTON- WOBURN- INTERSTATE PAVEMENT PRESERVATION AND RELATED WORK ON I-95 Resurfacing Interstate DESIGN 2027
603008 WOBURN- BRIDGE REPLACEMENT, W-43-003, SALEM STREET OVER MBTA Bridge Replacement COMPLETE
604650 WOBURN- INTERSTATE RESURFACING ON I-95 Resurfacing COMPLETE
604652 STONEHAM- WINCHESTER- WOBURN- TRI-COMMUNITY BIKEWAY INCLUDING NEW BRIDGE, W-43-029, OVER THE ABERJONA RIVER Bikeway/Bike Path Construction COMPLETE
604878 READING- STONEHAM- WINCHESTER- WOBURN- INTERSTATE MAINTENANCE & RELATED WORK ON I-93 Resurfacing COMPLETE
604879 WILMINGTON- WOBURN- INTERSTATE MAINTENANCE & RELATED WORK ON ROUTE I-93 Resurfacing COMPLETE
604935 WOBURN- RECONSTRUCTION OF MONTVALE AVENUE, FROM I-93 INTERCHANGE TO CENTRAL STREET (APPROX. 1,850 FT) Hwy Reconstr - Minor Widening COMPLETE
605018 BURLINGTON- LEXINGTON- READING- WOBURN- TRAFFIC SIGN & GUIDE REPLACEMENT ON I-95 (SR 128) Sign Installation/Upgrading COMPLETE
605589 BURLINGTON- WOBURN- INTERSTATE MAINTENANCE & RELATED WORK ON I-95 Resurfacing COMPLETE
606432 LEXINGTON- BURLINGTON- WOBURN- STONEHAM- READING- WAKEFIELD- LYNNFIELD- EXPANSION OF FIBER & CCTV ON I-95 Intelligent Transportation Sys COMPLETE
608219 READING- WAKEFIELD- INTERSTATE MAINTENANCE AND RELATED WORK ON I-95 Resurfacing Interstate COMPLETE
608763 BOSTON- SOMERVILLE- MEDFORD- STONEHAM- WOBURN- READING- HIGHWAY LIGHTING REHABILITATION ON I-93 (PHASE II) Lighting COMPLETE