Projects
Filter projects by: Project Phase TIP Status
All Projects All Projects
Construction Current Fiscal Year
Design Future Years
Complete Not Programmed
Number Description Project Type Status TIP Year
113100 CARVER- KINGSTON- PLYMPTON- RELOCATION OF A SECTION OF ROUTE 44 INCLUDING 6 BRIDGES (SECTION I) Highway Relocation COMPLETE
602564 CARVER- MIDDLEBOROUGH- BRIDGE REPLACEMENT, C-04-004=M-18-025, ROCHESTER ROAD OVER WEWEANTIC RIVER Bridge Replacement COMPLETE
603846 CARVER- MIDDLEBOROUGH- RESURFACING AND RELATED WORK ON A SECTION OF ROUTE 44 Resurfacing COMPLETE
606007 CARVER: FAP# STP-002S(743)X ROADWAY RECONSTRUCTION AND RELATED WORK (INCLUDING SIGNALS) ALONG A SECTION OF ROUTE 58 (MAIN STREET) (606007) Resurfacing COMPLETE
608455 PLYMOUTH- KINGSTON- CARVER- PLYMPTON- RESURFACING AND RELATED WORK ON ROUTE 44 (FROM MM 28.8 TO 36.4) Resurfacing DOT Owned Non-Interstate COMPLETE