| Project Description: |
WAYLAND- BRIDGE REPLACEMENT, W-11-001, ROUTE 20 OVER THE SUDBURY RIVER
The subject bridge will be removed and replaced in its existing alignment. A temporary bridge will be in place during construction to maintain existing traffic patterns.
|
| Location: |
|
| Resident Engineer: | Nitin Patel![]() |
| Construction Contract Value: | $5,356,086.00 |
| Construction Bid Price: | $4,762,715.00 |
| Initial Construction Estimate: | $3,834,891.06 |
| District: | District 3 |
|