ANDOVER- BRIDGE DECK REPLACEMENT, A-09-038, ROUTE 28 OVER ROUTE 125
This project involves replacing the bridge deck, including the roadway surface, for the Route 28 bridge over Route 125.
Location:
  • Town of Andover
  • Resident Engineer: John McGillicuddy
    Construction Contract Value: $3,370,358.00
    Construction Bid Price: $2,867,635.00
    Initial Construction Estimate: $4,247,070.00
    District: District 4

    Contracts (3) Progress
    # 36570 -- Design -- Bridge Rehab/Recon/New Const
    Provide design services for the rehabilitation of existing bridges, structural evaluations and emergency design support services. Final
    # 57462 -- Design -- Bridge Open End
    Work will consist of providing engineering design, review and construction management services on a task order basis. Final
    # 66333 -- Construction Contract
    Bridge Rehabilitation (Including Painting) – (A-09-038) (Steel) – Route 28 (Main Street) over Route 125. Completed

    Bridges

    Contract Dates
    Notice to Proceed: 11/16/2010
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 08/21/2008
    Project Review Committee PRC Approved 11/06/2008
    Project Review Committee Letter 12/01/2008
    Project Status Initiated 10/20/2005
    Project Status Advertised 07/24/2010
    Project Management
    100% Design 100% Package Received 12/21/2009
    75% Design 75% Package Received 07/10/2009
    75% Design 75% Package Comments to DE 11/23/2009
    Final Design PS&E Received 07/06/2010
    Final Design PS&E to FAPRO 07/21/2010