| Project Description: | LAWRENCE- OXFORD PAPER MILL DEMOLITION CONTRACT, BR# L-04-017 CANAL STREET OVER SPICKETT RIVER This is the advance demolition contract for the construction of a new Canal Street bridge over the existing historic bridge.  It includes thirteen historic dilapidated brick buildings/structures and three crossings over the raceway.  The demolition is expected to be completed by January 24, 2005. | 
| Location: |  | 
| Resident Engineer: | Ted Gibson  | 
| Construction Contract Value: | $3,486,207.00 | 
| Initial Construction Estimate: | $3,721,387.30 | 
| District: | District 4 | 
| Current Status: | Contractor will be working at night the next two weeks on a barrier issue and during the day doing loam and seed work. This job should be complete by June 1, 2007. (as of 05/07/2007) | 
| 