| Project Description: |
LAWRENCE- OXFORD PAPER MILL DEMOLITION CONTRACT, BR# L-04-017 CANAL STREET OVER SPICKETT RIVER
This is the advance demolition contract for the construction of a new Canal Street bridge over the existing historic bridge. It includes thirteen historic dilapidated brick buildings/structures and three crossings over the raceway. The demolition is expected to be completed by January 24, 2005.
|
| Location: |
|
| Resident Engineer: | Ted Gibson![]() |
| Construction Contract Value: | $3,486,207.00 |
| Initial Construction Estimate: | $3,721,387.30 |
| District: | District 4 |
| Current Status: | Contractor will be working at night the next two weeks on a barrier issue and during the day doing loam and seed work. This job should be complete by June 1, 2007. (as of 05/07/2007) |
|