Project Description:
NEWTON- WESTON- BRIDGE REHABILITATION, N-12-010=W-29-005, COMMONWEALTH AVENUE (ROUTE 30) OVER THE CHARLES RIVER
The purpose of this project is to rehabilitate the deck of the bridge that carries Commonwealth Avenue (Route 30) over the Charles River.
Location:
  • City of Newton
  • Town of Weston
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Construction Begins: Autumn 2024
    Project Manager: Robert P Antico
    Estimated Total Contract Cost: $25,784,282.15
    Estimated Total Federal Participating Construction Cost: $27,233,841.72
    Funding Provision: This project is planned to be funded through the 2024 Transportation Improvement Program for the Boston Metropolitan Planning Organization.
    District: District 6
    Current Status: This project has been advertised for construction bids. (as of 07/27/2024 )

    Contracts (2) Progress
    # 115768 -- Design -- Services
    Statewide - Master Service Agreement for design and review services. Final
    # 77865 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2024
    Responsible MPO: Boston Metropolitan Planning Organization
    Location: Municipality
    Cities: NEWTON
    WESTON
    Category: Advertised Projects Constr.
    Budget Section: 1A
    Advance Construct: No
    Air Quality Exempt: No

  • NHPP = 21,851,750 Project proposed by MassDOT, not scored.
  • Added $5,469,625 of HIP-BR via STIP Action 7.
  • Category FA - Hwy Infrast. Prgm (HIPBR) - Bridge
    Federal Cost: $4,375,700.00
    State Cost: $1,093,925.00
    Total Cost: $5,469,625.00
    Category FA - Ntl. Hwy Perform. Prgm (NHPP) - On-System Bridge
    Federal Cost: $17,481,400.00
    State Cost: $4,370,350.00
    Total Cost: $21,851,750.00

    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 08/02/2007
    Project Review Committee PRC Tabled 06/12/2008
    Project Review Committee PRC Approved 11/06/2008
    Project Review Committee Letter 12/01/2008
    Project Status Advertised 07/27/2024
    Project Management
    100% Design 100% Package Received 06/08/2023
    100% Design 100% Package Received - Resub 1 04/04/2024
    25% Design 25% Package Received 12/12/2019
    25% Design 25% Package Received 02/03/2022
    25% Design Design Public Hearing 08/11/2021
    25% Design 25% Plans Complete 08/11/2021
    75% Design 75% Package Received 02/03/2022
    Final Design PS&E Received 05/02/2024
    Final Design PS&E to FAPRO 05/14/2024
    Final Design PS&E Received - Resub 1 06/05/2024
    Final Design PS&E Received - Resub 2 07/08/2024