| Project Description: |
PALMER- BRIDGE REPLACEMENT, BR# P-01-024, ROUTE 20 (PARK STREET) OVER CSX & ROUTE 67 NORTHBOUND
The existing bridge will be demolished and replaced with a new bridge approximately 100 feet to the south. The new bridge location provides a greater degree of safety through the provision of a straighter roadway alignment.
|
| Location: |
|
| Resident Engineer: | George Pelletier![]() |
| Construction Contract Value: | $6,024,506.00 |
| Construction Bid Price: | $5,276,279.00 |
| Initial Construction Estimate: | $5,578,307.00 |
| District: | District 2 |
| Current Status: | Bridge under construction. (as of 05/17/2006) |
| Additional Info: | Daily lane restrictions/reductions during the work week. All lanes open at end of work day and weekends. (as of 02/15/2008) |
|