Project Description:
CARVER- KINGSTON- PLYMPTON- RELOCATION OF A SECTION OF ROUTE 44 INCLUDING 6 BRIDGES (SECTION I)
Section I is the third and final construction phase for this three-segment project. It is the continuation of the Route 44 Relocation from the Section II limits, and proceeds westerly through Kingston, Plympton, and Carver, extending 0.6 miles west of the Route 58 & Route 44 Intersection and terminating in Middleboro. This section includes two interchanges at Route 58 and Spring Street and an emergency westbound exit ramp at Route 80. A new five-span 300 feet bridge over the Winnetuxet River will be included.
Location:
  • Town of Carver
  • Town of Kingston
  • Town of Plympton
  • Resident Engineer: Robert Fitzgerald
    Construction Contract Value: $51,640,298.16
    Construction Bid Price: $31,917,980.41
    Initial Construction Estimate: $44,669,283.30
    District: District 5

    Contracts (2) Progress
    # 30140 -- Construction Contract
    RTR 44 RELOCATION (SECT. 1) Completed
    # 94187 -- Design -- Highway
    ROUTE 44 - FINAL DES. SEC I&II Final

    Bridges

    Contract Dates
    Notice to Proceed: 01/26/2001
    Contract Information
    Project Designer: Consultant
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Status Advertised 12/27/1997
    Project Management
    25% Design Design Public Hearing 11/29/1989