Project Description:
OXFORD- ROADWAY RECONSTRUCTION AND RELATED WORK AT INTERSECTION OF COMINS ROAD, MILL STREET AND ROUTE 56
The work consists of roadway widening, pavement resurfacing, installing a fully actuated traffic signal, and replacing bridge railings and related work at the intersection of Comins Road, Mill Street and Route 56 in Oxford. This project begins approximately 800 feet south of the Comins Road / Route 56 intersection and extends approximately 770 feet to the north on Route 56. The work will also consist of placing new bituminous concrete berm, resetting granite edging or curb, resetting or stacking existing guardrail, and installing new guardrail. New drainage structures include catchbasins, drain manholes and reinforced concrete pipe will be installed to provide adequate roadway drainage. Proposed roadway striping includes striping an exclusive left turn lane for both Route 56 approaches.
Location:
  • Town of Oxford
  • Design Responsibility: Municipality
    Right of Way Responsibility: Other
    Project Manager: Marie Joyce Rose
    Estimated Total Federal Participating Construction Cost: N/A
    District: District 3
    Current Status: This project has been advertised for construction bids. (as of 05/18/2002 )

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

  • - none -
  • See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Status Advertised 08/11/2001
    Project Status Advertised 05/18/2002
    Project Management