Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
WAREHAM- RECONSTRUCTION OF ROUTE 6 & 28, FROM 500 FT. EAST OF TYLER AVENUE TO RED BROOK ROAD (1.65 MILES)
Work on this project includes the reconstruction of Route 6/28 to provide a cross section consisting of 4 travel lanes (2 lanes in each direction separated by a median), bicycle accommodating shoulders, and sidewalks on both sides of the roadway. Traffic signals will be upgraded at Cranberry Drive Plaza/Home Depot Drive, Cinema Drive and Main Avenue. A new traffic signal system will be added at Red Brook Road. All traffic signal equipment be new or replaced and will include pedestrian indications compliant with the Americans with Disabilities Act (ADA). Accommodations for U- turn are designed at each intersection. There is also an exclusive left turn lane with a U-turn bubble between Cinema Drive and Main Street. The existing drainage system will be replaced with a new drainage system. The stormwater will be treated using best management practices. The project also includes new signs and pavement markings.
Location:
  • Town of Wareham
  • Construction Begins: Spring 2019
    Resident Engineer: Ian Bettencourt
    Construction Bid Price: $17,372,109.00
    District: District 5
    Current Status: •Bell Traffic on site installing wire for lighting sitewide. PA Landers will be starting EWO#17 Monday 4/22/24 by installing conduit across the road at 3 locations EB & WB (Highway Lighting R&R) PJ Keating scheduled for milling on 4/29/24-5/1/24 (6A-6P) Paving ops following week Cosco installing bounds Normal work hours are Monday thru Thursday 6:00 AM to 4:30 PM. Expect periodic lane closures and restrictions.. (as of 04/23/2024)

    Contracts (4) Progress
    # 105995 -- Construction Contract
    Roadway Reconstruction and Related Work (Including Signals) along a Section of Route 6 & 28 (Cranberry Highway). 87% Complete
    # 55347 -- Design -- Highway
    Work will consist of providing preliminary design, final engineering design and construction phase services for the reconstruction of Route 6 & 28 in Wareham. Final
    # 64325 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 77887 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 04/10/2019
    Contract Information
    Project Designer: Consultant
    Funding Source: FED. AID. ACCELERATED BRIDGE
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 04/28/1988
    Project Status Advertised 09/22/2018
    Project Management
    100% Design 100% Package Received 03/23/2016
    100% Design 100% Package Comments to DE 09/08/2016
    25% Design 25% Package Received 07/02/2010
    25% Design 25% Package Comments to DE 02/17/2012
    25% Design Design Public Hearing 07/12/2012
    75% Design 75% Package Received 06/25/2014
    75% Design 75% Package Comments to DE 07/01/2015
    Final Design PS&E Received 01/05/2018
    Final Design PS&E Received - Resub 1 08/21/2018
    Consultant Contract Process Scope to DE 09/17/2008
    Consultant Contract Process NTP Issued 04/16/2009