Project Description: |
REVERE- BRIDGE REPLACEMENT, BR# R-05-011, REVERE STREET OVER THE MBTA - B&M RAILROADS
The proposed project consists of the replacement of the bridge structure and the reconstruction of the bridge approaches
|
Location: |
|
Resident Engineer: | Leonard Bodkins |
Construction Contract Value: | $5,480,156.00 |
Construction Bid Price: | $3,391,090.25 |
Initial Construction Estimate: | $2,977,522.53 |
District: | District 4 |
Current Status: | Pavement markings completed. Signing is completed. Project substansially complete. (as of 10/22/2008) |
|