BOSTON- BRIDGE REPLACEMENT, BR# B-16-204, SILVER STREET OVER THE HAUL ROAD & CONRAIL
The roadway width will be 4.3 meters curb to curb and the bridge will include sidewalks on both sides that are 1.6 meters wide. The bridge will be closed during construction and traffic will be detoured.
Location:
  • City of Boston
  • Resident Engineer: Girard Allien
    Construction Contract Value: $1,187,144.00
    Construction Bid Price: $1,068,222.40
    Initial Construction Estimate: $695,410.00
    District: District 4
    Current Status: All work on this project was completed as of June 23, 2006. (as of 12/28/2007)

    Contracts (2) Progress
    # 42177 -- Construction Contract
    Boston - Silver St./Haul Rd. & Conrail Completed
    # 95257 -- Design -- Bridge Open End
    OFF SYSTEM FAID BR-RND 4 CONTF Final

    Bridges

    Contract Dates
    Notice to Proceed: 09/02/2005
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    All work on this project was completed as of June 23, 2006.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 07/15/1997
    Project Status Advertised 08/14/2004
    Project Management
    25% Design Design Public Hearing 09/29/1999
    75% Design 75% Package Received 03/23/2000
    75% Design 75% Package Comments to DE 08/24/2000
    Final Design PS&E Received 08/05/2004
    Final Design PS&E to FAPRO 08/05/2004