Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
BOSTON- BRIDGE REPLACEMENT, BR# B-16-172, SPRAGUE STREET OVER MBTA, CSX & ACCESS
The purpose of the project is to replace the existing bridge which carries Sprague Street over the MBTA, CSC, and Service Road in the City of Boston. The proposed replacement bridge will be a four span superstructure approximately 450 feet in length with sidewalks on both sides. The existing abutments will be modified to accommodate the new bridge superstructure. The existing stone pier will be removed and 3 new concrete piers will be constructed to support the new superstructure. During construction a temporary pedestrian bridge will be in place.
Location:
  • City of Boston
  • Resident Engineer: Harry Thompson Iii
    Construction Contract Value: $7,968,708.89
    Construction Bid Price: $7,853,388.00
    Initial Construction Estimate: $6,822,417.00
    District: District 4
    Current Status: This project is 100% complete. (as of 08/21/2008)

    Contracts (3) Progress
    # 43300 -- Construction Contract
    Boston - Bridge Replacement (B-16-172) - Sprague Street over the MBTA CSX and Service Road Completed
    # 58595 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to the MassHighway on an open end basis for various statewide highway and bridge projects. Final
    # 97461 -- Design -- Bridge Rehab/Recon/New Const
    Boston-Sprague St/Conrail & T Final

    Bridges

    Contract Dates
    Notice to Proceed: 12/14/2005
    Contract Information
    Project Designer: Consultant
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    This project is 100% complete.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Status Advertised 09/25/2004
    Project Management
    100% Design 100% Package Received 12/13/2004
    100% Design 100% Package Comments to DE 07/21/2004
    25% Design 25% Package Received 07/19/1999
    25% Design 25% Package Comments to DE 10/06/1999
    25% Design Design Public Hearing 04/05/2000
    75% Design 75% Package Received 08/22/2001
    75% Design 75% Package Comments to DE 01/28/2002
    75% Design 75% Plans Complete 05/12/2004
    Final Design PS&E Received 09/14/2004
    Final Design PS&E to FAPRO 09/14/2004