| Project Description: |
ATTLEBORO- BRIDGE REPLACEMENT AND ROADWAY RELOCATION, BR# A-16-026 THATCHER STREET OVER MBTA/CONRAIL/AMTRAK
The existing bridge will be demolished and replaced with a new bridge approximately 50 feet to the northeast. The new bridge location provides a greater degree of safety through the provision of a straighter roadway alignment of Thacher Street.
|
| Location: |
|
| Resident Engineer: | William Staubin![]() |
| Construction Contract Value: | $5,173,414.76 |
| Construction Bid Price: | $4,829,727.00 |
| Initial Construction Estimate: | $4,840,353.50 |
| District: | District 5 |
|