Project Description:
LAWRENCE- BRIDGE REHABILITATION, L-04-003, UNION STREET OVER THE MERRIMACK RIVER (DUCK BRIDGE)
This is a bridge rehabilitation project. This bridge carries Union Street over Merrimack River in Lawrence. In construction the bridge will be closed with provisions for pedestrian traffic. The rehabilitation will be accomplished by replacing the steel deck, repairing the trusses and their supports, and providing a new concrete deck for the length of the bridge.
Location:
  • City of Lawrence
  • Resident Engineer: Jeffrey Lavallee
    Construction Contract Value: $19,905,638.76
    Construction Bid Price: $17,150,896.00
    Initial Construction Estimate: $19,608,134.46
    District: District 4

    Contracts (2) Progress
    # 57727 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassHighway on an open end basis for various highway and bridge projects. Final
    # 57757 -- Construction Contract
    Bridge Rehabilitation (Including Painting) (L-04-003) (Duck Bridge) - Union Street over the Merrimack River. Completed

    Bridges

    Contract Dates
    Notice to Proceed: 04/22/2009
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 10/07/1997
    Project Status Advertised 09/20/2008
    Project Management
    100% Design 100% Package Received 04/10/2007
    100% Design 100% Package Comments to DE 10/17/2007
    25% Design 25% Package Comments to DE 01/07/2005
    25% Design Design Public Hearing 04/15/2004
    25% Design 25% Plans Complete 05/24/2004
    75% Design 75% Package Received 04/20/2005
    75% Design 75% Package Comments to DE 09/12/2005
    Final Design PS&E Received 08/29/2008