| Project Description: |
MIDDLEFIELD- BRIDGE REPLACEMENT, BR# M-19-009 CLARK WRIGHT ROAD OVER GLENDALE BROOK
|
| Location: |
|
| Design Responsibility: | Consultant |
| Right of Way Responsibility: | Other |
| Project Manager: | Bruce Sylvia![]() |
| Estimated Total Federal Participating Construction Cost: | N/A |
| District: | District 1 |
| Current Status: | This project has been advertised for construction bids. (as of 12/14/1996 ) |
|
Bridges
|
||||||
|
|
|
|||||||||||