WESTFIELD- BRIDGE REPLACEMENT, W-25-011, POCHASSIC STREET OVER THE PV RAILROAD & ACCESS ROAD
The purpose of this project is to construct a new bridge carrying Pochassic Street over the PV Railroad upon the existing abutments. Pochassic Street will be closed for vehicle traffic during construction and a temporary bridge will be provided for pedestrian and bicyclist access.
Location:
  • City of Westfield
  • Resident Engineer: Sean Milligan
    Construction Contract Value: $2,885,744.00
    Construction Bid Price: $2,654,716.00
    Initial Construction Estimate: $3,986,625.05
    District: District 2

    Contracts (7) Progress
    # 37075 -- Design -- Footprint Bridge contracts
    (Footprint 6) Perform design on deficient State and/or municipally owned bridges as part of the bridge Rehbilitation/Replacement/Preservation Program. Final
    # 41489 -- Design -- Geotechnical
    Statewide - implement geophysical methods on statewide designed and constructed bridge and highway projects. Final
    # 57727 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassHighway on an open end basis for various highway and bridge projects. Final
    # 57915 -- Design -- Services
    Work will consist of providing engineering design services to the MassHighway on an open end basis for Layout and Right of Way assignments. Final
    # 64308 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 64316 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 70933 -- Construction Contract
    Bridge Replacement Br. No. W-25-011 (Concrete) Pochassic Street over the PV Railroad and Access Road. Completed

    Bridges

    Contract Dates
    Notice to Proceed: 04/05/2012
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 04/21/2005
    Project Review Committee Letter 06/03/2005
    Project Status Advertised 09/03/2011
    Project Management
    100% Design 100% Package Received 07/05/2011
    100% Design 100% Package Comments to DE 07/20/2011
    25% Design 25% Package Received 07/07/2006
    25% Design 25% Package Comments to DE 01/13/2010
    25% Design 25% Package Comments to DE 02/17/2011
    25% Design 25% Package Comments to DE 04/01/2011
    25% Design Design Public Hearing 01/27/2011
    75% Design 75% Package Received 03/17/2011
    Final Design PS&E Received 09/06/2011
    Final Design PS&E to FAPRO 08/31/2011
    Consultant Contract Process Scope to DE 11/29/2005
    Consultant Contract Process NTP Issued 02/14/2006