Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
CAMBRIDGE- BRIDGE REPLACEMENT, BR# C-01-013, WALDEN STREET OVER THE B & M RAILROAD AND MBTA
The purpose of this project is to replace the existing two span substandard bridge with a new two span continuous bridge. The historic brick arch cattle path will be rehabilitated. The proposed project limits on Walden Street extend from approximately the intersection of Richdale Avenue and Walden Street to approximately 15 feet beyond the intersection of King Street and Walden Street.
Location:
  • City of Cambridge
  • Resident Engineer: Sean Magnus
    Construction Contract Value: $5,072,513.49
    Construction Bid Price: $4,184,918.25
    Initial Construction Estimate: $3,036,154.12
    District: District 4

    Contracts (2) Progress
    # 45304 -- Construction Contract
    Cambridge - Bridge Rehabilitation (C-01-013) (Concrete) - Walden St. over the B&M RR and MBTA Completed
    # 96044 -- Design -- Bridge Open End
    RD 3 F/A Non-NHS Bridges-Con O Final

    Bridges

    Contract Dates
    Notice to Proceed: 08/08/2006
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Status Advertised 09/24/2005
    Project Management
    100% Design 100% Package Received 08/18/2003
    100% Design 100% Package Received 04/27/2005
    100% Design 100% Package Received 04/27/2005
    100% Design 100% Package Comments to DE 07/21/2004
    100% Design 100% Plans Complete 07/21/2004
    25% Design Design Public Hearing 04/25/2000
    25% Design 25% Plans Complete 02/05/1999
    75% Design 75% Package Received 01/27/2003
    75% Design 75% Package Comments to DE 05/23/2003
    Final Design PS&E Received 08/25/2005
    Final Design PS&E to FAPRO 08/25/2005