Project Description: |
LANCASTER- LEOMINSTER- INTERCHANGE IMPROVEMENTS ON ROUTE 2 AT EXIT 34
The project consists of constructing a new Route 2 westbound off ramp, new eastbound on and off ramps, and removing the existing ramps. Improvements are also being made to the Harvard Street and Old Union Turnpike intersection.
|
Location: |
|
Resident Engineer: | -- not assigned -- |
Construction Contract Value: | $5,267,990.58 |
Construction Bid Price: | $1,746,470.00 |
Initial Construction Estimate: | $1,639,939.00 |
District: | District 3 |
Current Status: | The project is now substantially complete. The contractor is anticipated to be finished with the remaining work and the punch list over the next few weeks. (as of 01/06/2006) |
|
Bridges |
|
|
|
|