SHARON- BRIDGE REPLACEMENT, BR# S-09-004 DEPOT STREET OVER THE MBTA & AMTRAK
Location:
  • Town of Sharon
  • Resident Engineer: William Staubin
    Construction Contract Value: $4,360,641.17
    Initial Construction Estimate: $5,156,810.50
    District: District 5

    Contracts (1) Progress
    # 97341 -- Construction Contract
    Bridge Replacement - Depot Street over the MBTA and AMTRAK. Completed

    Bridges

    Contract Dates
    Notice to Proceed: 04/29/1997
    Contract Information
    Project Designer: Consultant
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Status Advertised 03/02/1996
    Project Management