KINGSTON- BRIDGE REPLACEMENT, K-01-002, ELM STREET OVER THE JONES RIVER
This project consists of the replacement of a structurally deficient town-owned bridge in the Town of Kingston. The existing bridge was closed to traffic and MassHighway provided a temporary ACROW Panel bridge to span the existing structure until a replacement could be constructed. The temporary bridge remains in place until a more permanent structure can be designed that meets design standards. The existing, structurally deficient bridge is to be replaced with a precast concrete structure or precast NEXT beam structure.
Location:
  • Town of Kingston
  • Resident Engineer: Kenneth Belgrave
    Construction Contract Value: $2,925,514.48
    Construction Bid Price: $2,036,598.80
    Initial Construction Estimate: $2,135,587.65
    District: District 5

    Contracts (3) Progress
    # 55040 -- Design -- Bridge Rehab/Recon/New Const
    Work will consist of structural evaluations and emergency design support services to support the Bridge Preservation/Betterment Advertisement Program. Final
    # 57463 -- Design -- Bridge Open End
    Work will consist of providing engineering design, review and construction management services on a task order basis. Final
    # 71092 -- Construction Contract
    Bridge Replacement (K-01-002) (Concrete) Elm Street over the Jones River. (ABP) Completed

    Bridges

    Contract Dates
    Notice to Proceed: 02/21/2012
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 01/25/1996
    Project Status Advertised 09/17/2011
    Project Management
    25% Design 25% Package Received 03/08/2010
    25% Design Design Public Hearing 05/06/2010
    75% Design 75% Package Received 01/24/2011
    75% Design 75% Package Comments to DE 03/22/2011
    Final Design PS&E Received 06/27/2011
    Final Design PS&E to FAPRO 09/14/2011
    Consultant Contract Process Scope to DE 09/25/2009
    Consultant Contract Process NTP Issued 12/04/2009