LYNN- SAUGUS- BRIDGE REPLACEMENT (TEMP), L-18-016=S-05-008, ROUTE 107 OVER THE SAUGUS RIVER (FOX HILL BRIDGE)
The work includes the construction of a 2-lane temporary moveable bridge. This temporary bridge will remain in use until such time that a permanent bridge can be built in the same location as the existing bridge. The horizontal clearance under the bridge will be 50 feet.
Location:
  • City of Lynn
  • Town of Saugus
  • Resident Engineer: John Lepore
    Construction Contract Value: $11,807,096.00
    Construction Bid Price: $10,399,815.00
    Initial Construction Estimate: $11,965,762.00
    District: District 4

    Contracts (3) Progress
    # 51302 -- Design -- Hwy Eng Open End
    Statewide - work will consist of providing engineering design and review services to the MassHighway on an open end basis for various statewide highway and bridge projects. Final
    # 59936 -- Construction Contract
    Bridge Replacement (L-18-0016T=S-05-008T) (Steel) (Temporary) - Route 107 over the Saugus River. Completed
    # 93106 -- Design -- Bridge Rehab/Recon/New Const
    LYNN/SAUGUS, BELDEN BLY BR. Final

    Bridges

    Contract Dates
    Notice to Proceed: 12/08/2009
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 09/08/1980
    Project Status Advertised 06/20/2009
    Project Management
    100% Design 100% Package Received 01/18/2006
    100% Design 100% Package Comments to DE 08/13/2007
    25% Design 25% Package Received 08/09/2000
    25% Design 25% Package Comments to DE 08/13/2002
    25% Design Design Public Hearing 12/20/2007
    75% Design 75% Package Received 08/10/2004
    75% Design 75% Package Comments to DE 05/10/2005
    Final Design PS&E Received 06/05/2009
    Final Design PS&E to FAPRO 06/16/2009
    Consultant Contract Process Scope to DE 01/14/1992
    Consultant Contract Process NTP Issued 05/11/1994
    Consultant Contract Process Workhours Approved 07/03/1992