Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
BEDFORD- CROSBY DRIVE MIDDLESEX TURNPIKE CONSTRUCTION (PHASE I)
The proposed roadway begins approximately 375 feet north of Route 62 to the Crosby Drive/Middlesex Turnpike intersection. There are no signalized intersections in this section. Improvements include widening from a two-lane to a five-lane roadway with two travel lanes in each direction. A shared two way left turn lane, sidewalk, grass strip, storm water systems, stone masonry retaining wall and landscaping will also be provided.
Location:
  • Town of Bedford
  • Resident Engineer: Anthony Neve
    Construction Contract Value: $4,059,758.00
    Construction Bid Price: $3,997,626.00
    Initial Construction Estimate: $3,872,594.00
    District: District 4
    Current Status: The contractor has nearly completed this project. A final inspection was held in late June 2007. Only a minor punch list remains. (as of 07/09/2007)

    Contracts (1) Progress
    # 37520 -- Construction Contract
    Bedford - Crosby Drive (Middlesex Turnpike) Phase I Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 03/29/2005
    Contract Information
    Project Designer: Municipality
    Funding Source: HIGH PRIORITY PROJECTS
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    The contractor has nearly completed this project. A final inspection was held in late June 2007. Only a minor punch list remains.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 04/16/2004
    Project Review Committee PRC Approved 02/25/1997
    Project Status Advertised 09/04/2004
    Project Management
    100% Design 100% Package Received 09/08/2003
    100% Design 100% Package Comments to DE 03/05/2004
    100% Design 100% Plans Complete 12/25/2003
    25% Design 25% Package Comments to DE 03/30/1998
    75% Design 75% Package Received 03/08/2002
    75% Design 75% Package Comments to DE 07/16/2002
    75% Design 75% Plans Complete 08/14/2003
    Final Design PS&E Received 08/10/2004
    Final Design PS&E to FAPRO 08/10/2004
    Consultant Contract Process NTP Issued 05/07/2004