Project Description:
BEDFORD- BILLERICA- BURLINGTON- MIDDLESEX TURNPIKE/MITRE EXTENSION FROM ROUTE 62 TO NORTH OF PLANK STREET (PHASE II)
The proposed full depth reconstruction includes Middlesex Turnpike and the Mitre Extension: from the Mitre Extension intersection with Route 62 and Network Drive to 800 feet north of the Plank Street/Middlesex Turnpike/Crosby Drive intersection, for a total distance of 6,844 feet. Also included is Plank Street: from Middlesex Turnpike to approximately 480 feet north of Middlesex Turnpike. The intersections that will be improved within this section are the Mitre Extension/Route 62/Network Drive intersection, and the Middlesex Turnpike/Plank Street Intersection. The proposed work includes two travel lanes in each direction with the addition of turning lanes for safety and signalized intersections, a median and landscaping.
Location:
  • Town of Bedford
  • Town of Billerica
  • Town of Burlington
  • Resident Engineer: Jay Patel
    Construction Contract Value: $12,581,982.00
    Construction Bid Price: $11,744,277.60
    Initial Construction Estimate: $13,589,788.50
    District: District 4

    Contracts (2) Progress
    # 54138 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to the MassHighway on an open end basis for various statewide highway and bridge projects. Final
    # 63316 -- Construction Contract
    Construction of Phase II of the Middlesex Turnpike Extension. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 06/30/2010
    Contract Information
    Project Designer: Municipality
    Funding Source: Highway Safety Improvement Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    Wetlands Replication
    The advancement of the design is currently on hold pending the siting of a wetlands replication area.
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 01/05/1987
    Project Status Advertised 09/19/2009
    Project Management
    100% Design 100% Package Received 02/01/2008
    100% Design 100% Package Comments to DE 11/17/2008
    25% Design Design Public Hearing 10/12/2000
    25% Design Design Public Hearing 06/02/2009
    75% Design 75% Package Received 03/21/2002
    75% Design 75% Package Received 03/08/2007
    75% Design 75% Package Comments to DE 11/01/2007
    Final Design PS&E Received 08/12/2009
    Final Design PS&E to FAPRO 09/16/2009