BEDFORD- BILLERICA- MIDDLESEX TURNPIKE IMPROVEMENTS, FROM CROSBY DRIVE NORTH TO MANNING ROAD, INCLUDES RECONSTRUCTION OF B-04-006 (PHASE III)
The proposed roadway improvements begin 800 feet north of the Plank Street/Middlesex Turnpike/Crosby Drive intersection to approximately 900 feet north of Manning Road. On Lexington Road, approximately 550 feet on each approach to the Middlesex Turnpike. On Manning Road, approximately 550 feet on each approach to Middlesex Turnpike. The intersections that will be improved within this section are the Middlesex Turnpike/Oak Park intersection, the Middlesex Turnpike/900 Middlesex Turnpike drive intersection, the Middlesex Turnpike/Lexington Road intersection and the Middlesex Turnpike/Manning Road intersection. The traffic signal improvements at the Middlesex Turnpike/Albion Way intersection will be completed by others, and therefore are included in this scope of work. The proposed work includes two travel lanes in each direction with the addition of turning lanes for safety and signalized intersections, a median and landscaping. Reconstruction of the bridge over the Shawsheen River is included with this project.
Location:
  • Town of Bedford
  • Town of Billerica
  • Construction Begins: Summer 2017
    Resident Engineer: Greg Kwon
    Construction Bid Price: $34,475,000.00
    District: District 4

    Contracts (4) Progress
    # 71613 -- Design -- Bridge Open End
    Work will consist of providing engineering design services to MassDOT on a task order basis for bridge, traffic and utility permit structural design and analysis assignments. Final
    # 77863 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 77887 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 97932 -- Construction Contract
    Construction of Phase III of the Middlesex Turnpike Extension. 91% Complete

    Bridges

    Contract Dates
    Notice to Proceed: 08/31/2017
    Contract Information
    Project Designer: Municipality
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 01/05/1987
    Project Status Advertised 09/24/2016
    Project Management
    100% Design 100% Package Received 03/07/2016
    100% Design 100% Package Comments to DE 04/29/2016
    25% Design Design Public Hearing 10/12/2000
    25% Design Design Public Hearing 05/09/2016
    75% Design 75% Package Received 05/08/2007
    75% Design 75% Package Received 05/08/2014
    75% Design 75% Package Comments to DE 12/12/2014
    Final Design PS&E Received 02/07/2017
    Final Design PS&E to Peer Reviewer 08/08/2016
    Final Design Peer Review Comments to DE 09/06/2016
    Final Design PS&E to FAPRO 09/09/2016