BOSTON- DEDHAM- BRIDGE REPLACEMENT, BR# B-16-177=D-05-006 ROUTE 109 (BRIDGE STREET/SPRING STREET) OVER THE CHARLES RIVER
The proposed project consists of rehabilitating the existing Route 109 bridge, over the Charles River, in its present location with minor improvements to the approach roadways. The bridge will remain open to traffic during construction.
Location:
  • City of Boston
  • Town of Dedham
  • Resident Engineer: Edward Moschella Jr
    Construction Contract Value: $5,000,038.32
    Initial Construction Estimate: $1,392,231.50
    District: District 4
    Current Status: This project has been completed. (as of 07/21/2005)

    Contracts (1) Progress
    # 31360 -- Construction Contract
    Bridge Replacement (Concrete) - Route 109 (Bridge Street/Spring Street) over the Charles River. (SECOND RE-ADVERTISMENT) PRE - BID CONFERENCE 05/18/01 Completed

    Bridges

    Contract Dates
    Notice to Proceed: 07/26/2001
    Contract Information
    Project Designer: Consultant
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    This project has been completed.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 02/06/1996
    Project Status Advertised 11/02/1996
    Project Status Advertised 02/17/2001
    Project Status Advertised 05/12/2001