Project Description: |
CANTON- BRIDGE REPLACEMENT, BR# C-02-008 RELOCATED HIGH STREET OVER MBTA AND AMTRAK
The work consists of partial demolition of the existing bridge substructure, demolition of the existing bridge superstructure and construction of a 3 span multiple steel stringer bridge.
|
Location: |
|
Resident Engineer: | Brian Zilinsky |
Construction Contract Value: | $2,333,561.12 |
Construction Bid Price: | $1,977,482.00 |
Initial Construction Estimate: | $2,593,400.00 |
District: | District 4 |
Current Status: | All work complete with the exception of the extra work to furnish and install a holding - dissipation ponding area to eliminate drainage problems-70%complete. (as of 10/10/2006) |
Additional Info: | A 45 day extension of time may be needed to process all materials documentaion and project information. (as of 10/10/2006) |
|