Project Description:
SOMERVILLE- BRIDGE REPLACEMENTS, BR# S-17-011, LOWELL STREET OVER THE MBTA & B&M R.R. & S-17-015 LOWELL OVER THE MBTA AND B&MRR
The work consists of the demolition and the replacement of 2 bridges on Lowell Street over the MBTA and the B&M Rail Road. Existing abutments will be modified to accommodate the new bridges. A parapet wall and protective screen will be constructed on both sides of the bridges and the full length of the road between the two bridges.
Location:
  • City of Somerville
  • Resident Engineer: Harry Thompson Iii
    Construction Contract Value: $2,507,230.00
    Construction Bid Price: $2,175,991.00
    Initial Construction Estimate: $1,801,447.00
    District: District 4
    Current Status: This project is complete (as of 09/06/2006)

    Contracts (2) Progress
    # 34636 -- Construction Contract
    Two Bridges Replacement S-17-11 & S-17-15 - Lowell Street over B&M RR and MBTA. Completed
    # 98082 -- Design -- Bridge Rehab/Recon/New Const
    SOMERVILLE- BRIDGE REHABILITATION, BR# S-17-011 LOWELL STREET OVER THE MBTA & B&M R.R. & S-17-015 LOWELL OVER THE MBTA AND B&MRR Final

    Bridges

    Contract Dates
    Notice to Proceed: 06/14/2004
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    This project is complete
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Status Advertised 03/13/2004
    Project Management