OAK BLUFFS- TISBURY- BRIDGE REPLACEMENT (TEMP) O-01-001=T-04-001, BEACH ROAD OVER LAGOON POND
This project consists of the construction of a temporary bascule (movable) bridge, Beach Road over Lagoon Pond. The temporary bridge will be parallel to the existing bridge, which will be removed. The total bridge length will be 300 feet long. The total project length including associated approach roadway work is 1,200 feet. The bridge will be made of premanufactured galvanized steel trusses.
Location:
  • Town of Oak Bluffs
  • Town of Tisbury
  • Resident Engineer: Michael McGovern
    Construction Contract Value: $10,281,890.36
    Construction Bid Price: $9,199,524.00
    Initial Construction Estimate: $6,752,650.00
    District: District 5

    Contracts (3) Progress
    # 43766 -- Design -- Hwy Eng Open End
    Preparation and review of Layout plans and written descriptions on various projects statewide. Final
    # 51231 -- Construction Contract
    Oak Bluffs - Tisbury - Bridge Construction (O-01-001=T04-004) Beach Road over Lagoon Pond Completed
    # 54829 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review servicesto MassHighway on an open end basis for various statewide highway and bridge projects. Final

    Bridges

    Contract Dates
    Notice to Proceed: 05/29/2007
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Status Advertised 08/26/2006
    Project Status Advertised 03/03/2007
    Project Management
    25% Design 25% Package Received 03/31/2003
    25% Design 25% Package Comments to DE 07/20/2004
    25% Design Design Public Hearing 11/24/2003
    75% Design 75% Package Received 12/01/2004
    75% Design 75% Package Comments to DE 04/08/2005
    Final Design PS&E Received 09/05/2005
    Final Design PS&E to FAPRO 11/05/2005