Project Description:
ATTLEBORO- BRIDGE REPLACEMENT, A-16-025, OLIVE STREET OVER MBTA/AMTRAK
This project consists of replacing the existing state-owned three-span plate-girder bridge, approximately 180 feet long, with a three-span prestressed-concrete-box-beam bridge, approximately 160 feet long. The proposed bridge will span over four tracks, which are used by Amtrak (electrified), MBTA and CSX. The project also includes the reconstruction of Olive Street from the Ten-Mile River Bridge to and including the intersection with Ellis Street, a distance of 1,300 linear feet.
Location:
  • City of Attleboro
  • Resident Engineer: Aleksey Belov
    Construction Contract Value: $8,732,982.00
    Construction Bid Price: $7,134,159.00
    Initial Construction Estimate: $7,953,821.50
    District: District 5

    Contracts (5) Progress
    # 54830 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassHighway on an open end basis for various statewide highway and bridge projects. Final
    # 54836 -- Design -- Bridge Rehab/Recon/New Const
    Work will consist of structural evaluations and emergency design support services to support the Bridge Preservation/Betterment Advertisement Program. Final
    # 57915 -- Design -- Services
    Work will consist of providing engineering design services to the MassHighway on an open end basis for Layout and Right of Way assignments. Final
    # 68145 -- Construction Contract
    Bridge Replacement (A-16-025) (Concrete) Olive Street over the AMTRAK and MBTA Railroads (ABP) Completed
    # 97314 -- Design -- Local Design Contract
    OLIVE ST. OVER MBTA/AMTRAK/CONRAIL Final

    Bridges

    Contract Dates
    Notice to Proceed: 04/29/2011
    Contract Information
    Project Designer: Consultant
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Status Advertised 09/18/2010
    Project Status Advertised 03/12/2011
    Project Management
    25% Design 25% Package Received 04/17/2009
    25% Design Design Public Hearing 06/25/2009
    75% Design 75% Package Received 09/14/2009
    75% Design 75% Package Comments to DE 01/05/2010
    Final Design PS&E Received 07/19/2010
    Final Design PS&E to FAPRO 09/18/2010
    Consultant Contract Process NTP Issued 04/17/2009