Project Description:
FALMOUTH- BRIDGE REPLACEMENT, F-03-008, PALMER AVENUE OVER THE BAY COLONY RAILROAD
The project includes the complete replacement of the bridge over the proposed Shining Sea Bikeway. A detour will be in place during the construction effort for pedestrians and vehicles. The project includes new guardrail, pavement markings and curbing.
Location:
  • Town of Falmouth
  • Resident Engineer: Michael McGovern
    Construction Contract Value: $1,531,930.00
    Construction Bid Price: $1,511,630.00
    Initial Construction Estimate: $1,878,589.70
    District: District 5

    Contracts (2) Progress
    # 53243 -- Construction Contract
    Falmouth - Bridge Replacement (F-3-8) - Palmer Avenue over Shining Sea Bikepath Terminated
    # 94470 -- Design -- Footprint Bridge contracts
    CONTH FTPRT-RD2 FA NON-NHS STP Final

    Bridges

    Contract Dates
    Notice to Proceed: 01/14/2008
    Contract Information
    Project Designer: Consultant
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 02/06/1996
    Project Status Advertised 09/16/2006
    Project Management
    100% Design 100% Package Received 06/21/2006
    100% Design 100% Package Comments to DE 08/18/2006
    25% Design 25% Package Comments to DE 12/12/2001
    25% Design Design Public Hearing 04/30/2002
    75% Design 75% Package Received 10/22/2004
    75% Design 75% Package Received 07/11/2005
    75% Design 75% Package Comments to DE 09/01/2005
    Final Design PS&E Received 06/23/2006
    Final Design PS&E Received 11/14/2006
    Final Design PS&E to FAPRO 06/30/2006