FALMOUTH- BRIDGE REPLACEMENT, F-03-008, PALMER AVENUE OVER THE BAY COLONY RAILROAD
The project includes the complete replacement of the bridge over the proposed Shining Sea Bikeway. A detour will be in place during the construction effort for pedestrians and vehicles. The project includes new guardrail, pavement markings and curbing.
|
| Location: |
|
| Resident Engineer: | Michael McGovern![]() |
| Construction Contract Value: | $1,531,930.00 |
| Construction Bid Price: | $1,511,630.00 |
| Initial Construction Estimate: | $1,878,589.70 |
| District: | District 5 |
|