Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
HAVERHILL- RECONSTRUCTION OF ROUTE 125 (SOUTH MAIN ST), FROM BOSTON ROAD TO BASILIERE BRIDGE & SALEM STREET, FROM SOUTH MAIN STREET TO PEABODY STREET
The work consists of modifications to the horizontal and vertical alignment, installation of new and upgrades of existing traffic signals, drainage improvements, full depth pavement widening, granite curb, cement concrete sidewalk, signing, striping and restorative landscaping.
Location:
  • City of Haverhill
  • Resident Engineer: Michael Sherwood
    Construction Contract Value: $13,171,386.00
    Construction Bid Price: $13,075,663.55
    Initial Construction Estimate: $14,644,110.00
    District: District 4

    Contracts (1) Progress
    # 67098 -- Construction Contract
    Roadway Reconstruction and Related Work on a Section of Route 125 (South Main Street) and Salem Street. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 02/08/2011
    Contract Information
    Project Designer: Municipality
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 03/04/1993
    Project Review Committee PRC Approved 11/30/1993
    Project Review Committee Letter 12/15/1993
    Project Status Advertised 08/28/2010
    Project Management
    100% Design 100% Package Received 10/13/2009
    100% Design 100% Package Comments to DE 12/29/2009
    25% Design 25% Package Received 07/16/1999
    25% Design 25% Package Comments to DE 03/16/2000
    25% Design Design Public Hearing 08/16/2000
    75% Design 75% Package Received 11/03/2008
    75% Design 75% Package Comments to DE 03/20/2009
    Final Design PS&E Received 08/18/2010
    Final Design PS&E to FAPRO 08/23/2010
    Consultant Contract Process NTP Issued 04/18/2008