Project Description:
BEVERLY- RECONSTRUCTION & SIGNAL IMPROVEMENTS ON ROUTE 1A (RANTOUL STREET & CABOT STREET), FROM CABOT STREET (SOUTH) TO 440 FEET NORTH OF BLAINE AVENUE, INCLUDES CULVERT REPAIR OF B-11-008
Approximately 5,750 feet of pavement rehabilitation on Rantoul Street will improve safety, traffic flow, and roadway drainage. The width of the existing roadway will remain approximately the same. Turning lanes will be added at the Elliott Street intersection and the existing traffic signals at School Street, Federal Street and Elliott Street will be upgraded to meet current standards. The 11-foot sidewalks and granite curbing will be refurbished throughout the project and will include wheelchair access ramps at all crossing points.
Location:
  • City of Beverly
  • Resident Engineer: Carmen Ilardi
    Construction Contract Value: $24,595,209.55
    Construction Bid Price: $19,874,365.50
    Initial Construction Estimate: $18,274,000.00
    District: District 4

    Contracts (4) Progress
    # 64315 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 64325 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 77887 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 85012 -- Construction Contract
    Roadway Reconstruction and Related Work (Including Signals and MBTA Track Work) along a Section of Route 1A (Rantoul and Cabot Streets) Completed

    Bridges

    Contract Dates
    Notice to Proceed: 06/17/2015
    Contract Information
    Project Designer: Municipality
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 10/28/1993
    Project Status Initiated 11/15/2005
    Project Status Advertised 09/20/2014
    Project Management
    100% Design 100% Package Received 08/06/2014
    100% Design 100% Package Comments to DE 09/03/2014
    25% Design 25% Package Received 12/24/2009
    25% Design 25% Package Comments to DE 08/22/2011
    25% Design Design Public Hearing 05/30/2013
    75% Design 75% Package Received 10/18/2013
    75% Design 75% Package Received 03/07/2014
    75% Design 75% Package Received 05/29/2014
    75% Design 75% Package Received 06/13/2014
    75% Design 75% Package Comments to DE 01/16/2014
    75% Design 75% Package Comments to DE 07/25/2014
    Final Design PS&E Received 09/16/2014
    Final Design PS&E to FAPRO 09/17/2014
    Consultant Contract Process NTP Issued 09/04/2008