Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
MIDDLETON- SAFETY IMPROVEMENTS/CHANNELIZATION ROUTE 114 (NORTH MAIN STREET)
This project will signalize the intersection at Route 114, Essex Street, and Forest Street to provide safe and controlled traffic movements through this intersection. Work along Route 114 shall extend from Middleton Square to approximately 600 feet north of the Essex and Forest Streets intersection. Work on Essex Street shall extend from the intersection of Route 114 to a point approximately 200 feet north of the intersection. Work on Forest Street shall extend from the intersection of Route 114 to a point approximately 200 feet west of the intersection. A traffic channelization island will also be included on Essex Street at the intersection of Route 114.
Location:
  • Town of Middleton
  • Resident Engineer: Bernard LaVita
    Construction Contract Value: $2,842,356.71
    Construction Bid Price: $2,187,229.00
    Initial Construction Estimate: $1,877,333.50
    District: District 4
    Current Status: Final inspection on this project was held and this project is complete. (as of 10/22/2008)

    Contracts (1) Progress
    # 42297 -- Construction Contract
    Middleton - North Main St (Rte 114), Safety Improvement and Related Work, PF #600227 Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 09/22/2005
    Contract Information
    Project Designer: Municipality
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    Final inspection on this project was held and this project is complete.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 03/02/1993
    Project Review Committee PRC Approved 09/09/1993
    Project Status Advertised 04/16/2005
    Project Management
    100% Design 100% Package Received 09/11/1998
    100% Design 100% Package Comments to DE 12/02/1998
    25% Design 25% Package Received 04/12/1996
    25% Design 25% Package Comments to DE 07/01/1996
    25% Design Design Public Hearing 08/08/1996
    75% Design 75% Package Received 12/04/1996
    75% Design 75% Package Comments to DE 02/01/1997
    Final Design PS&E Received 11/15/2004
    Final Design PS&E to FAPRO 03/25/2005