Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
TAUNTON- RECONSTRUCTION OF ROUTE 138, FROM BAKER STREET TO WEIR STREET (10,000 FT +/-)
The proposed project will consist of reconstructing Somerset Avenue and Lawton Street from the intersection of East and West Baker Street to Weir Street for approximately 9900 feet. Also included are curbing, cement concrete sidewalks to ADA standards, traffic signals reconstruction, drainage improvements, pavement markings, signing and all other incidental work necessary.
Location:
  • City of Taunton
  • Resident Engineer: Gary Dixon
    Construction Contract Value: $7,502,780.34
    Construction Bid Price: $6,285,862.50
    Initial Construction Estimate: $7,602,477.50
    District: District 5

    Contracts (1) Progress
    # 51675 -- Construction Contract
    Taunton - Roadway Reconstruction and Related Work on a Section of Route 138 (Somerset Avenue) Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 10/16/2007
    Contract Information
    Project Designer: Municipality
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 09/30/1993
    Project Status Advertised 09/23/2006
    Project Management
    100% Design 100% Package Received 07/14/2006
    100% Design 100% Package Comments to DE 08/22/2006
    25% Design 25% Package Received 02/04/1997
    25% Design 25% Package Comments to DE 12/15/1997
    25% Design Design Public Hearing 03/12/1998
    75% Design 75% Package Received 04/01/2005
    75% Design 75% Package Comments to DE 12/14/2005
    Final Design PS&E to FAPRO 09/14/2006