Project Description: |
MILLBURY- BRIDGE REPLACEMENT, BR# M-22-003 RIVERLIN STREET OVER THE BLACKSTONE RIVER
The work consists of the reconstruction of the Riverlin Street bridge over the Blackstone River. The project limits extend from the southerly approach to the bridge to the Riverlin Street/Canal Street/Grafton Street intersection. This intersection will be signalized.
|
Location: |
|
Resident Engineer: | Thomas Donnelly |
Construction Contract Value: | $1,030,191.00 |
Construction Bid Price: | $973,191.00 |
Initial Construction Estimate: | $714,000.00 |
District: | District 3 |
Current Status: | Signals are anticipated to be turned from flash to regular operation on 04/19/2005. (as of 04/14/2005) |
|
Bridges
|
|
|
|
|