LAKEVILLE- MIDDLEBOROUGH- RELOCATION OF ROUTE 79 (RHODE ISLAND ROAD)
This project consists of the relocation of Route 79 across land formerly belonging to the Lakeville State Hospital and now proposed for commercial development. The .5 mile segment of new infrastructure will relocate Route 79 away from the I-495 ramps and facilitate the signalization of those ramps to improve the overall operation and safety of Exit 4 in Middleborough located approximately .25 miles distant. Work also includes installation of signals on Route 105 and coordination with CANPRO development and the MBTA to address needs at the Lakeville Train Station.
Location:
  • Town of Lakeville
  • Town of Middleborough
  • Resident Engineer: Kenneth White
    Construction Contract Value: $2,372,332.00
    Construction Bid Price: $1,989,029.10
    Initial Construction Estimate: $2,810,492.00
    District: District 5

    Contracts (2) Progress
    # 59682 -- Construction Contract
    Roadway Relocation and Related Work on a Section of Route 79 (Rhode Island Road. Completed
    # 64309 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 11/06/2009
    Contract Information
    Project Designer: Other
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 07/26/2007
    Project Review Committee PRC Approved 12/09/1993
    Project Review Committee Letter 07/26/2007
    Project Status Initiated 03/12/2007
    Project Status Advertised 07/04/2009
    Project Management
    100% Design 100% Package Received 11/03/2008
    100% Design 100% Package Comments to DE 02/02/2009
    25% Design 25% Package Received 07/24/2007
    25% Design 25% Package Comments to DE 02/04/2008
    25% Design Design Public Hearing 03/19/2008
    75% Design 75% Package Received 06/24/2008
    75% Design 75% Package Comments to DE 08/29/2008
    Final Design PS&E Received 03/16/2009
    Final Design PS&E to FAPRO 06/26/2009