Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
PEMBROKE- REHABILITATION OF ROUTE 36 (CENTER STREET) FROM ROUTE 27 TO ROUTE 14
The proposed project consists of the resurfacing/rehabilitation and full depth reconstruction of certain areas of Route 36 (Center Street) from the intersection with Route 27 in the south to the intersection with Route 14 to the north. Sidewalks will be constructed and reconstructed. Drainage will be upgraded. The project also includes sign and pavement markings.
Location:
  • Town of Pembroke
  • Construction Begins: Winter 2021/2022
    Resident Engineer: Trevor O'Bryan
    Construction Bid Price: $8,857,852.00
    District: District 5
    Current Status: GC working on punch list items. Future Operations: General Cleanup for winter shutdown. Normal work hours are Monday through Friday, 7:00 AM to 3:30 PM. Expect periodic lane closures and restrictions. (as of 11/01/2024)
    Additional Info: No traffic set-ups are expected. Roadway open. (as of 11/01/2024)

    Contracts (1) Progress
    # 116949 -- Construction Contract
    Roadway Reconstruction and Related Work on a Section of Route 36 (Center Street) 95% Complete

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 03/09/2022
    Contract Information
    Project Designer: Municipality
    Funding Source: FA - Surface Trans. Block Grant (STBG)
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    Current Status
    GC working on punch list items. Future Operations: General Cleanup for winter shutdown. Normal work hours are Monday through Friday, 7:00 AM to 3:30 PM. Expect periodic lane closures and restrictions.
    Additional Info
    No traffic set-ups are expected. Roadway open.
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 08/20/1996
    Project Status Advertised 12/11/2021
    Project Management
    100% Design 100% Package Received 04/08/2019
    100% Design 100% Package Comments to DE 07/25/2019
    25% Design 25% Package Received 01/12/2011
    25% Design 25% Package Received 09/30/2011
    25% Design 25% Package Comments to DE 05/25/2011
    25% Design Design Public Hearing 10/23/2013
    75% Design 75% Package Received 08/10/2016
    75% Design 75% Package Comments to DE 03/01/2017
    Final Design PS&E Received 01/15/2020
    Final Design PS&E Received - Resub 1 06/02/2021
    Final Design PS&E Received - Resub 2 11/16/2021