Project Description:
RAYNHAM- RESURFACING AND RELATED WORK, SOUTH MAIN STREET (ROUTE 104)
The proposed work along Route 104 in the Town of Raynham begins from the corporate boundary with the City of Taunton to the North Main Street/Orchard Street/Pleasant Street intersection. The proposed work on South Main Street consists of cold planing and overlay of the existing pavement surface, as well as the installation of new granite curb and sidewalks on both sides of the roadway, and drainage modifications. The total length of the project is 1.6 miles.
Location:
  • Town of Raynham
  • Resident Engineer: Gary Dixon
    Construction Contract Value: $5,687,084.12
    Construction Bid Price: $1,716,732.05
    Initial Construction Estimate: $1,615,983.50
    District: District 5

    Contracts (1) Progress
    # 41806 -- Construction Contract
    Raynham - South Main St, Resurfacing & Related Work, Project File #600390 Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 07/15/2005
    Contract Information
    Project Designer: Municipality
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Status Advertised 12/08/2001
    Project Status Advertised 09/11/2004
    Project Status Advertised 01/29/2005
    Project Management
    100% Design 100% Package Received 08/20/2004
    100% Design 100% Package Comments to DE 12/13/2004
    Final Design PS&E Received 01/14/2005
    Final Design PS&E to FAPRO 01/14/2005