EAST BRIDGEWATER- HANSON- RECONSTRUCTION OF ROUTE 27 (FRANKLIN STREET)
The reconstruction of Franklin Street begins at the Whitman Town Line and continues towards the Hanson Town Line for about one-half mile. The project also includes a new traffic signal at the Route 14 intersection (Oak Street/ West Washington Street).
Location:
  • Town of East Bridgewater
  • Town of Hanson
  • Resident Engineer: Robert Fitzgerald
    Construction Contract Value: $3,094,887.48
    Construction Bid Price: $2,099,696.50
    Initial Construction Estimate: $1,808,924.00
    District: District 5

    Contracts (1) Progress
    # 42438 -- Construction Contract
    East Bridgewater - Hanson - Reconstruction on Franklin St. (Rte 27) and a Section of West Washington St. (Rte 14) Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 11/15/2005
    Contract Information
    Project Designer: Municipality
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Status Advertised 04/16/2005
    Project Management
    100% Design 100% Package Received 05/18/2004
    100% Design 100% Package Comments to DE 07/21/2004
    25% Design 25% Package Received 12/09/1996
    25% Design 25% Package Comments to DE 05/28/1998
    75% Design 75% Package Received 03/15/2000
    75% Design 75% Package Comments to DE 11/27/2000
    75% Design 75% Plans Complete 05/24/2004
    Final Design PS&E Received 07/23/2004
    Final Design PS&E to FAPRO 09/22/2004