Project Description: |
EASTON- RESURFACING AND RELATED WORK ON ROUTE 123 (DEPOT STREET)
This is a Town project consisting of resurfacing and related work on Town owned Route 123 from BlackBrook Road to Route 138.
|
Location: |
|
Resident Engineer: | John Bielski |
Construction Contract Value: | $1,376,173.00 |
Construction Bid Price: | $1,092,430.20 |
Initial Construction Estimate: | $1,091,147.00 |
District: | District 5 |
|