HANOVER- RESURFACING AND RELATED WORK ON ROUTE 123 (WEBSTER STREET)
The proposed project consists of widening, flattening, straightening and resurfacing the existing paved roadway and improvements to the existing drainage system. The project begins at the Rockland Town Line and runs easterly to the Norwell Town Line. One lane of traffic in each direction shall be maintained at all times throughout the construction period.
|
Location: |
|
Resident Engineer: | Peter Benkart |
Construction Contract Value: | $5,341,079.58 |
Construction Bid Price: | $3,394,298.42 |
Initial Construction Estimate: | $2,718,995.00 |
District: | District 5 |
|