Project Description: |
COHASSET- HINGHAM- ROADWAY RECONSTRUCTION ON A SECTION OF ROUTE 228 (MAIN ST., SHORT ST., LEAVITT ST., EAST ST., HULL ST.)
Work done under this contract consists of cold plane and pavement overlay, full depth pavement construction, signal replacement, minor drainage improvements and adjustments, curbing installation and adjustment, highway guard upgrading, signing, safety controls during construction, pavement markings, erosion control and related work.
|
Location: |
|
Design Responsibility: | Municipality |
Right of Way Responsibility: | Other |
Project Manager: | Thomas Loughlin |
Estimated Total Federal Participating Construction Cost: | N/A |
District: | District 5 |
Current Status: | This project has been advertised for construction bids. (as of 09/30/2000 ) |
|