Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
KINGSTON- RECONSTRUCTION OF ROUTE 27 (PEMBROKE STREET)
The proposed project will maintain and improve the existing roadway from the Pembroke Town line to just short of the intersection of Evergreen Street, a distance of 3.3 miles. Traffic will be allowed during construction. Included is minor widening, a new drainage system, new sidewalk, guardrail installation, pavement markings, new traffic signals, landscaping and new signage.
Location:
  • Town of Kingston
  • Resident Engineer: Robert Fitzgerald
    Construction Contract Value: $10,538,012.00
    Construction Bid Price: $9,582,813.00
    Initial Construction Estimate: $9,777,919.00
    District: District 5

    Contracts (1) Progress
    # 54038 -- Construction Contract
    Kingston - Roadway Reconstruction and Related Work on Route 27 (Pembroke Street) Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 03/31/2008
    Contract Information
    Project Designer: Municipality
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 12/11/1996
    Project Status Approved 25% 01/21/2000
    Project Status Advertised 09/08/2007
    Project Management
    100% Design 100% Package Received 10/23/2000
    100% Design 100% Package Comments to DE 01/31/2001
    25% Design 25% Package Received 02/04/1998
    25% Design 25% Package Comments to DE 04/30/1998
    25% Design Design Public Hearing 12/15/1998
    25% Design 25% Plans Complete 01/14/2000
    75% Design 75% Package Received 08/20/1999
    75% Design 75% Package Comments to DE 02/18/2000
    Final Design PS&E Received 02/09/2006
    Final Design PS&E Received 07/21/2006
    Final Design PS&E Received 10/04/2006
    Final Design PS&E Received 11/02/2006
    Final Design PS&E Received 02/21/2007
    Final Design PS&E Received 07/23/2007
    Final Design PS&E to FAPRO 09/06/2007