Project Description:
DARTMOUTH- RECONSTRUCTION OF FAUNCE CORNER ROAD & IMPROVEMENTS TO I-195 RAMPS & INTERSECTIONS, INCLUDES REPLACEMENT OF D-04-016 OVER I-195
This project involves the replacement of the existing bridge carrying Faunce Corner Road (FCR) over I-195, and the realignment of Faunce Corner Road; reconstruction of the intersections of Faunce Corner Road/Cross Road/Comfort Lane, Faunce Corner Road/I-195 Eastbound On/Off ramps and Faunce Corner Road/I-195 Westbound On/Off ramps; realignment and reconstruction of the ramps and acceleration lanes/shoulders of I-195 Eastbound and Westbound and the installation of traffic signal system at three (3) locations.
Location:
  • Town of Dartmouth
  • Resident Engineer: Francis Grenon
    Construction Contract Value: $20,847,334.10
    Construction Bid Price: $18,596,285.00
    Initial Construction Estimate: $18,886,358.75
    District: District 5

    Contracts (6) Progress
    # 51098 -- Design -- Bridge Rehab/Recon/New Const
    Work includes design for reconstructing Bridge D-04-016 carrying Faunce Corner Road over Interstate Route 195 in Dartmouth. Final
    # 59587 -- Design -- Bridge Open End
    Work will consist of providing engineering design and review services to MassHighway on an open end basis for various statewide highway and bridge ABP projects. Final
    # 64323 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 68386 -- Design -- Bridge Open End
    Work will consist of providing engineering design and review services to MassDOT on an open end basis for various statewide highway and bridge projects. Final
    # 77864 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 79744 -- Construction Contract
    Roadway Reconstruction and Related Work of Faunce Corner Road and Adjacent Ramps Including Bridge Replacement (D-04-016 ) (Concrete) Faunce Corner Road over Interstate 195. Completed

    Bridges

    Contract Dates
    Notice to Proceed: 08/08/2014
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 12/23/1993
    Project Status Initiated 11/17/2005
    Project Status Advertised 09/14/2013
    Project Management
    100% Design 100% Package Received 01/16/2013
    100% Design 100% Package Comments to DE 04/30/2013
    25% Design 25% Package Received 11/19/2009
    25% Design 25% Package Comments to DE 07/30/2012
    25% Design 25% Package Comments to DE 10/09/2012
    25% Design Design Public Hearing 11/02/2011
    75% Design 75% Package Received 05/21/2012
    75% Design 75% Package Comments to DE 10/03/2012
    Final Design PS&E Received 06/21/2013
    Final Design PS&E to FAPRO 09/09/2013
    Consultant Contract Process Scope to DE 04/10/2008
    Consultant Contract Process NTP Issued 09/24/2008
    Consultant Contract Process Workhours Approved 06/08/2008