Project Description:
AGAWAM- RECONSTRUCTION OF ROUTE 187 FROM 425 FT. SOUTH OF S. WESTFIELD STREET TO ROUTE 57 (0.3 MILES - PHASE I)
This project involves roadway improvements on South Westfield Street from 425 feet south of the South Westfield Street/Pine Street intersection to relocated Route 57, a distance of approximately .3 miles. The roadway will be widened to increase the shoulder width., minor alignment modifications will improve sight distance, and milling and resurfacing the roadway and new sidewalks.
Location:
  • City of Agawam
  • Construction Begins: Winter 2019/2020
    Resident Engineer: Mark Shea
    Construction Bid Price: $1,930,205.50
    District: District 2

    Contracts (1) Progress
    # 109100 -- Construction Contract
    Roadway Reconstruction and Related Work (Including Signals) along a Section of Pine Street (Route 187) (Phase 1) Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 01/30/2020
    Contract Information
    Project Designer: Municipality
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Review Committee PRC Approved 11/30/1993
    Project Status Advertised 07/27/2019
    Project Management
    100% Design 100% Package Received 11/26/2018
    100% Design 100% Package Comments to DE 01/18/2019
    25% Design 25% Package Received 09/06/1996
    25% Design 25% Package Received 02/01/2017
    25% Design 25% Package Comments to DE 02/13/1997
    25% Design 25% Package Comments to DE 06/16/2017
    25% Design Design Public Hearing 02/12/1998
    25% Design Design Public Hearing 11/14/2017
    75% Design 75% Package Received 05/03/2018
    75% Design 75% Package Received 07/03/2018
    75% Design 75% Package Comments to DE 09/12/2018
    Final Design PS&E Received 05/20/2019
    Final Design PS&E Received - Resub 1 06/24/2019