HINGHAM- INTERSECTION IMPROVEMENTS AT DERBY STREET, WHITING STREET (ROUTE 53) AND GARDNER STREET
Work on this project will consist of intersection improvements at Derby Street, Whiting Street (Route 53) and Gardner Street. Work includes the installation of a new traffic signal system and geometric modifications at the intersection. including left turn lanes on Derby Street. The project extends to the Cushing Street intersection and will also provide a turn lane at Recreation Park Road The project will also include improved accommodation for bicycles and pedestrians. .
Location:
  • Town of Hingham
  • Construction Begins: Autumn 2018
    Resident Engineer: Russell Davis
    Construction Bid Price: $2,436,413.19
    District: District 5

    Contracts (3) Progress
    # 104005 -- Construction Contract
    Intersection Improvements and Related Work (Including Signals) at (Route 53) Whiting, Derby and Gardner Streets Completed
    # 64315 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 77876 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 10/11/2018
    Contract Information
    Project Designer: Consultant
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Initiation Form PRC Submitted 11/16/1993
    Project Review Committee PRC Approved 05/13/2010
    Project Status Initiated 11/15/2005
    Project Status Advertised 05/19/2018
    Project Management
    100% Design 100% Package Received 11/08/2017
    100% Design 100% Package Comments to DE 02/12/2018
    25% Design 25% Package Received 12/28/2012
    25% Design 25% Package Comments to DE 11/13/2013
    25% Design Design Public Hearing 11/19/2014
    75% Design 75% Package Received 09/22/2015
    75% Design 75% Package Comments to DE 03/17/2016
    Final Design PS&E Received 04/17/2018
    Final Design PS&E to FAPRO 05/07/2018